top of page
  • Writer's pictureKaty Morgan

Introduction to AVIXA Certified Technology Specialist - Design (CTS-D) Exam

The AVIXA CTS-D Exam is challenging and thorough preparation is essential for success. This exam study guide is designed to help you prepare for the CTS-D certification exam. It contains a detailed list of the topics covered on the Professional exam, as well as a detailed list of preparation resources. These study guide for the AVIXA Certified Technology Specialist - Design will help guide you through the study process for your certification.

CTS-D pdf, CTS-D questions, CTS-D exam guide, CTS-D practice test, CTS-D books, CTS-D Syllabus, CTS-D

CTS-D AVIXA Certified Technology Specialist - Design Exam Summary


Exam Name: AVIXA Certified Technology Specialist - Design

Exam Code: CTS-D

Member Exam Price: $475 (USD)

Non-Member Exam Price: $575 (USD)

Duration: 180 mins

Number of Questions: 135

Passing Score: 350 / 500

Reference Books: Candidate Handbook

Schedule Exam: Pearson VUE

Sample Questions: AVIXA CTS-D Sample Questions

Recommended Practice: AVIXA CTS-D Certification Practice Exam

Exam Syllabus: CTS-D AVIXA Certified Technology Specialist - Design (CTS-D)

1. Domain 1: Conducting a Needs Assessment (16.8%)

● Task 1: Identify Decision-makers and Stakeholders

● Task 2: Identify Skill Level of End Users

● Task 3: Educate AV Clients

● Task 4: Review Client Technology Master Plan

● Task 5: Identify Client Expectations

● Task 6: Identify Scope of Work


2. Domain 2: Coordinating with Other Professionals to Develop Project Documentation (23.2%)

● Task 1: Review A/E (architectural and engineering) drawings

● Task 2: Coordinate with architectural/interior design professionals

● Task 3: Coordinate with Mechanical Professionals

● Task 4: Coordinate with Structural Professionals

● Task 5: Coordinate with Electrical Professionals

● Task 6: Coordinate with lighting professionals

● Task 7: Coordinate with IT and network security professionals

● Task 8: Coordinate with acoustical professionals

● Task 9: Coordinate with life safety and security professionals


3. Domain 3: Developing Designs (48%)

● Task 1: Create Draft AV Design

● Task 2: Confirm site conditions

● Task 3: Produce AV infrastructure drawings

● Task 4: Produce AV system drawings

● Task 5: Finalize Project Documentation


4. Domain 4: Conducting Project Implementation Activities (12%)

● Task 1: Participate in Project Implementation Communication

● Task 2: Conduct System Performance Verifications

● Task 3: Conduct Project Closeout Activities

AVIXA CTS-D Certification Sample Questions and Answers

To make you familiar with AVIXA Certified Technology Specialist - Design (CTS-D) certification exam structure, we have prepared this sample question set. We suggest you to try our Sample Questions for CTS-D - Design CTS-D Certification to test your understanding of AVIXA CTS-Dprocess with real AVIXA certification exam environment.


CTS-D AVIXA Certified Technology Specialist - Design Sample Questions:-


01. Which abbreviation on a drawing tells you that you will not need to install a specific display screen?

a) OFOI

b) OC

c) OD

d) NTS

02. The threshold of human hearing is 0 dB SPL at what kHz?

a) 0 kHz

b) 1 kHz

c) 3 kHz

d) 10 kHZ

03. What is the STC range for adequate privacy?

a) 0–20

b) 20–40

c) 40–55

d) 55–65

04. Calculating for loudspeaker coverage takes into account which of the following?

a) Ceiling height, listeners’ ear height, and the speaker’s angle of coverage

b) Dispersal patterns, room dimensions, and number of speakers

c) Number of speakers, type of speakers, acoustic treatments

d) Number of listeners, type of audio, speaker power

05. Which of the following are features of an audio signal generator?

a) Generates sine wave and other signals used for setting system levels

b) Usually has both 1 kHz and 400 Hz signal outputs

c) With a properly calibrated signal can determine signal bit rate

d) Can be helpful in measuring distortion

06. How do you determine the client’s long-term plans and needs in terms of equipment and support maintenance?

a) Ask advice from other AV industry experts and vendors

b) Contract with a consulting company to determine client needs

c) Consult the owner, examine standards and design manuals, and create the project report

d) Design a generic system that fits any organization of that size

07. When installing conduit, it is important to remember that the conduit will require the following:

a) Room to expand 45 percent because of latent heating

b) Internal insulation, usually an injected polyurethane jell

c) Adequate mounting support to withstand cable pulling

d) A slip sleeve to ensure adequate air space for cable

08. In which phase does a project manager need to work with allied trades to create proper workspaces?

a) Training phase

b) Installation phase

c) Maintenance phase

d) Design phase

09. What is the primary goal of a needs assessment?

a) Identifying the intended use of a space

b) Selecting the right equipment

c) Establishing the “first use” date

d) Meeting the budget requirements

10. According to best practices, what is the safe working load (SWL) requirement for overhead mounting of a 75 lb (34 kg) projector?

a) 500 lb (227 kg)

b) 375 lb (170 kg)

c) 300 lb (136 kg)

d) 275 lb (125 kg)


Answers:-


Answer 1:- a

Answer 2:- b

Answer 3:- c

Answer 4:- a

Answer 5:- a, b, d

Answer 6:- c

Answer 7:- c

Answer 8:- d

Answer 9:- a

Answer 10:- b